Stmicroelectronics Inc. Pension Restoration Plan v. Santoni

Citation: 316 F. App'x 556Docket: Nos. 07-15688, 07-16109

Court: Court of Appeals for the Ninth Circuit; November 16, 2008; Federal Appellate Court

Narrative Opinion Summary

In a contractual dispute, the plaintiffs, referred to as 'ST,' appealed a district court's summary judgment in favor of Annibale Santoni. The primary legal issue involved the integration of a written retirement plan under the Restatement (2d) of Contracts. Despite the absence of a merger clause, the court found the plan to be fully integrated and a comprehensive expression of the agreement between ST and its employees, aligning with established case law. The court noted that the retirement committee's interpretation of the plan, which conflicted with explicit terms, was impermissible. Additionally, ST's attempt to introduce extrinsic evidence was rejected, as it sought to contradict the clear and unambiguous language of the plan, particularly regarding benefits eligibility linked to citizenship status. The district court's decision that the committee abused its discretion by relying on inadmissible evidence was affirmed. Furthermore, the court opted not to adopt a more stringent de novo review standard suggested by Santoni, asserting that the judgment would remain consistent regardless of the standard applied. This disposition is non-precedential except as specified by applicable rules.

Legal Issues Addressed

Admissibility of Extrinsic Evidence

Application: The court determined that ST's extrinsic evidence, which contradicted the clear terms of the plan, was inadmissible.

Reasoning: Moreover, even if the plan were not fully integrated, ST's extrinsic evidence is inadmissible as it contradicts the written terms.

Contract Integration under Restatement (2d) of Contracts

Application: The court upheld the view that the written plan was a fully integrated agreement, rejecting arguments to the contrary due to lack of a merger clause.

Reasoning: ST did not successfully challenge the presumption that the written plan is fully integrated, as recognized by Restatement (2d) of Contracts.

Interpretation of Contractual Terms

Application: The court ruled that the retirement committee’s interpretation, which conflicted with the plan's explicit language, was unacceptable.

Reasoning: The committee's interpretation of the plan, which conflicted with its explicit language, was deemed unacceptable.

Standard of Judicial Review

Application: The court declined to apply a de novo review standard, indicating that the outcome would be unchanged under either standard.