Iowa Public Service Company (IPS) filed a complaint with the Iowa State Commerce Commission challenging the right of O’Brien County Rural Electric Cooperative (O’Brien) to provide electrical service to a rural water district within their assigned service areas, as defined by Iowa Code section 476.25. A hearing examiner upheld IPS's objection, granting it the right to serve the water district. O’Brien's appeal to the full commission was affirmed, with the commission applying a "geographic load center" test that determined the water district's electrical usage was concentrated in IPS's service area. The commission deemed O’Brien's evidence regarding potential changes in well usage as too speculative and ordered O’Brien to dismantle a transmission line it had illegally constructed without a franchise. Subsequent judicial review by the district court affirmed the commission's order, prompting O’Brien to appeal to a higher court, which also affirmed the ruling. The facts confirmed that the water district's well field consisted of four wells, with two located in IPS's area and two in O’Brien's. O’Brien's application for a franchise to construct a transmission line was withdrawn after IPS objected, leading to the installation of the line without proper authorization. On appeal, O’Brien contended that Iowa Code section 476.23(2) should govern the dispute, that it was not required to obtain a franchise, that the commission misapplied the geographic load test, and that failure to consider evidence regarding a new well warranted reversal.

The commission's action is challenged as arbitrary, capricious, and lacking substantial evidence, referencing Iowa Code section 17A.19(8)(f, g). The key issue is determining which statute, Iowa Code section 476.23(2) or 476.25, applies to electric service disputes for customers in multiple service areas. O’Brien argues that section 476.23(2) prohibits IPS from serving a well field in its territory, citing the statute's language that restricts utilities from serving customers unless they are closer than other utilities. O’Brien relies on the precedent set in Nishnabotna Valley Rural Electric Cooperative v. Iowa Power and Light Company, which emphasized the point of delivery as the crucial factor.

However, IPS contends that an amendment to section 476.23(2) allows exceptions when prospective customers are within an assigned exclusive service area. O’Brien claims this exception does not apply, arguing that Osceola falls within two service areas. The commission interpreted the statutory exclusion as applicable to cases involving customers spanning multiple areas, thus permitting the use of an alternative geographic load center test rather than strictly adhering to the point of delivery test.

While the commission's statutory interpretation is not binding, it is given weight in judicial analysis. The court agrees with the commission's interpretation that the point of delivery test typically restricts utilities from servicing new customers if another utility’s line is closer. However, this test has limitations, as it allows customers to strategically choose utilities by locating their delivery points. The commission highlighted that this could lead to inefficiencies in electric distribution and emphasized the importance of an area-designation approach as outlined in section 476.25 to achieve an economical distribution system for all utilities.

O’Brien’s interpretation of Iowa Code section 476.23(2) threatens the integrity of the point of delivery test when a customer spans multiple utility areas. The commission highlighted that maintaining this test could lead to numerous customer-maintained facilities, complicating safety oversight. O’Brien asserts that section 476.23(2) is clear and self-explanatory, arguing that section 476.25 does not address conflicts arising in multi-area scenarios. Even if ambiguity exists, O’Brien contends that its interpretation must prevail to avoid rendering the statute meaningless. 

In contrast, the commission and IPS emphasize the historical context of section 476.23, noting that the 1976 legislative amendments aimed to enhance coordinated electric service and reduce duplicative facilities. They argue that section 476.25, which establishes exclusive service areas, should take precedence, while section 476.23(2) remains applicable to areas not yet designated. O’Brien's proposed interpretation would exacerbate instability in territorial lines by allowing customers to artificially create multi-area designations for service.

The commission also references prior cases, indicating that earlier statutes lacked provisions for designated service areas, which were introduced in the 1976 amendments. The focus has since shifted from customer preference to territorial integrity, as reflected in the current statutes. Ultimately, the last sentence of section 476.23(2) provides an exception applicable to customers in exclusive service areas, irrespective of whether they occupy one or multiple territories, underscoring the relevance of a territorial approach for all customers.

The point of delivery test is not required by section 476.23(2), leading to the question of which test should be applied to resolve the dispute. O’Brien asserts that the point of delivery test, despite not being mandated, is the appropriate test. It claims that the adoption of the geographic load center test exceeded the commission’s authority under Iowa Code section 17A.19(8)(b) and violated its rights. Conversely, the commission and IPS argue that, since no specific test is mandated, the commission has discretion to use the geographic load center test. This test is defined as a theoretical location based on existing and future electric load installations, characterized as highly technical compared to the ordinary meaning of the point of delivery test. The geographic load center test aims to pinpoint where electrical usage is concentrated, avoiding complications associated with potential delivery points. The commission believes this test aligns with the policies of section 476.25, which seeks to reduce unnecessary duplication of electric utility facilities and promote efficient service. The commission maintains that establishing service areas for electric utilities is within its statutory authority and that the geographic load center test helps maintain territorial integrity and prevent conflicts. O’Brien claims it was unaware of the commission's application of this test, although it was previously used in a 1981 case. The commission’s reasoning is deemed rational and within its expertise. O’Brien also contends that the commission should have considered a potential water well in its computation. However, the commission found this development speculative as no permanent well existed, and thus, it did not abuse its discretion in excluding this evidence.

Determining the geographic load center for a customer requires clear information about their actual needs, as speculative data could lead to the creation of an artificial load center. Past cases, such as Nishnabotna, defined the center of electrical distribution based on 'permanent electric loads' expected to be installed. Although the district court disagreed with the commission's exclusion of certain evidence, it found that O'Brien was not prejudiced, as even with that evidence, the geographic load center test would still favor service by IPS. The commission ruled O’Brien's construction of a transmission line across a county road without a franchise was illegal, aligning with Iowa Code section 478.1, which mandates a franchise for such constructions. O’Brien argued for an exception under section 478.30, but the commission contended this section applies only when utility lines are already present on both sides of a road. While the court noted this interpretation is worthy of deference, it also stated that consideration of the illegal line would not affect the geographic load center determination, which remains in IPS's territory. O’Brien's argument about minimizing line duplication was weakened by the fact that construction began after a dispute was known. The court expressed skepticism about a utility building a line in a disputed area while claiming duplication as a concern. Ultimately, the commission's decision to disregard the line was upheld, and O’Brien's claims of substantial evidence and arbitrary decision-making were found to be unsubstantiated.

If the line was legally constructed, its existence must be factored into the decision-making regarding the utilities. The outcomes primarily influence the questions at hand. The court emphasizes that its review of the district court's examination of administrative actions is limited to verifying the correct application of the law. Agency findings are upheld on appeal if they are backed by substantial evidence, as per Iowa Code section 17A.19(8)(f). Furthermore, some deference is granted to the agency's expertise in interpreting relevant statutes. In this case, substantial evidence supports both the commission and district court's conclusions, indicating that the order was not arbitrary, capricious, or an abuse of discretion. The ruling is affirmed, with all justices concurring except for Justice Schultz, who dissents. The district court found that while the commission failed to consider the implications of switching wells, this oversight did not prejudice O’Brien, leading to the affirmation of the commission's order.