You are viewing a free summary from Descrybe.ai. For citation checking, legal issue analysis, and other advanced tools, explore our Legal Research Toolkit — not free, but close.

Turner-McCoy, Inc. v. Hardy

Citations: 230 Ark. 410; 323 S.W.2d 562; 1959 Ark. LEXIS 638Docket: 5-1844

Court: Supreme Court of Arkansas; April 20, 1959; Arkansas; State Supreme Court

Narrative Opinion Summary

This case involves a dispute over the priority of a mechanic’s and materialman’s lien claimed by a contractor relative to two mortgages recorded by the property owner’s financier. The contractor provided labor and materials for the construction of a manufacturing plant and later performed minor servicing work. After submitting invoices, the contractor filed suit to establish a lien for the total amount owed. The owner’s financier had previously recorded a substantial first mortgage, followed by a second mortgage to cover additional advances. The trial court accorded the contractor’s lien priority over the second mortgage but not the first. On appeal, the contractor argued its lien should relate back to the commencement of the project, while the financier cross-appealed to contest the lien’s validity altogether. The appellate court held that the statutory ninety-day period for perfecting a mechanic’s lien began upon substantial completion of the original contract, and minor post-completion servicing did not extend this period. Because the contractor did not file within the required ninety days, it failed to perfect its lien, resulting in both mortgages taking priority. The court affirmed the trial court’s decree on direct appeal, reversed on cross-appeal regarding the lien’s validity, and remanded for further proceedings.

Legal Issues Addressed

Appellate Disposition on Lien Priority and Perfection

Application: The appellate court affirmed the trial court's finding that the mortgages had priority over the mechanic’s lien and reversed to the extent that any lien rights were granted, remanding for further proceedings.

Reasoning: The decree is affirmed on direct appeal, reversed on cross-appeal, and the case is remanded for further proceedings, with Justice Robinson not participating.

Effect of Post-Completion Servicing Work on Lien Period

Application: Minor servicing or corrective work performed after the substantial completion of a contract does not extend or restart the ninety-day period for filing a mechanic’s lien.

Reasoning: These tasks were deemed mere servicing or corrective work on pre-installed machinery rather than new installations, which did not extend the lien period. According to legal precedent, such services post-installation do not constitute part of the original sale or installation, meaning the time to file a mechanic’s lien does not reset with these additional services.

Ninety-Day Period for Perfecting a Mechanic’s Lien

Application: The statutory period for perfecting a mechanic’s and materialman’s lien runs from the completion of the contract, and failure to file within ninety days after completion precludes the right to a lien.

Reasoning: Consequently, the appellant did not perfect its lien within the required ninety days after the contract's completion on March 14. As a result, the appellant is not entitled to a lien, affirming the priority of both appellee's mortgages.

Priority of Mechanic’s and Materialman’s Lien versus Recorded Mortgage

Application: The court considered whether a mechanic’s and materialman’s lien could take priority over a previously recorded mortgage when the work was completed after the mortgage was recorded.

Reasoning: The key issue on appeal was the priority of Turner-McCoy’s statutory lien, which they argued related back to the start of construction and thus was prior to the mortgage. However, the court found that Turner-McCoy completed its work by March 14, 1957, and did not file a lien notice or initiate suit within 90 days, leading to the conclusion that their lien was not superior to Mrs. Hardy’s mortgage.