Eugene Horbach, Individually and as Assignee of Tyrree Corporation, a Dissolved Illinois Corporation, and Eugene Horbach, on Behalf of Tyrree Corporation, a Dissolved Illinois Corporation v. Alvis Kaczmarek and One Three Six, Inc.

Docket: 99-3102

Court: Court of Appeals for the Seventh Circuit; April 30, 2002; Federal Appellate Court

EnglishEspañolSimplified EnglishEspañol Fácil
In 1989, TyrRee Corporation entered into a contract with Shred Pax Corporation to purchase a tire pyrolysis system, paying over $1.7 million but ultimately not accepting delivery due to dissatisfaction with the equipment. After TyrRee was dissolved in 1995, Eugene Horbach, its majority shareholder and assignee, sued Shred Pax (renamed One Three Six, Inc.) and its president, Alvis Kaczmarek, alleging breach of contract, fraud, rescission, unjust enrichment, and conversion. The district court dismissed the claims, ruling that the conversion claims were unsupported and the other claims were time-barred. 

The court accepted Horbach's allegations as true at this stage. TyrRee was formed in 1989, with Horbach owning 92% of the shares after acquiring Gellman's interest. A preliminary agreement for the tire pyrolysis system was signed on September 5, 1989, followed by a formal purchase order on September 26, which included the right for TyrRee to inspect and test the equipment before acceptance. After Shred Pax claimed readiness for testing in February 1990, TyrRee delayed acceptance due to site issues and requested modifications, leading to further delays and a storage fee arrangement. In April 1990, Shred Pax asserted that the modified system was ready, but TyrRee indicated it could not conduct testing until July, suggesting Shred Pax test the equipment instead. Shred Pax opted to continue collecting storage fees while waiting for TyrRee.

TyrRee was dissolved on September 9, 1990, and all rights under a letter agreement and purchase order were assigned to Horbach. On February 5, 1991, a Horbach agent inspected pyrolysis equipment in Portland, Oregon, finding only incomplete components that did not comply with the purchase order. Shred Pax informed Horbach that not all equipment was in Portland and that assembly would take 60 days, but acceptance testing never occurred. On April 18, 1991, Horbach's attorney canceled the purchase order due to Shred Pax’s failure to deliver compliant equipment, despite Horbach having paid over $1.76 million. Shred Pax refused to return the funds, leading Horbach to file suit in 1995. The district court dismissed all claims related to the purchase order, citing the breach of contract claim as untimely under Illinois' four-year limitation (810 ILCS 5/2-725(1)). The court determined the limitation period began on February 1, 1990, or at the latest, February 5, 1991, when the equipment's non-compliance was apparent. Horbach filed suit on September 11, 1995, exceeding the limitation period. Although Horbach claimed Shred Pax fraudulently concealed its breach, the court ruled that he had sufficient time to sue, thus the five-year limitation for fraudulent concealment (735 ILCS 5/13-215) did not apply. The court emphasized that existing case law did not support Horbach's position on the statute's interpretation.

The court dismissed Horbach's equitable claims for rescission and constructive trust based on the doctrine of laches, which applies when a plaintiff delays asserting a claim for an unreasonable time, causing prejudice to the defendant. This doctrine reflects the principle that courts are reluctant to assist parties who have neglected their rights to the detriment of others. In Illinois, if the statute of limitations for related legal claims has expired, laches can bar equitable claims even without proof of prejudice. Horbach's delay in filing suit until after the statute of limitations on his breach of contract claim had lapsed warranted the dismissal of his equitable claims.

Although the fraud claim was subject to a five-year limitations period, it was also deemed untimely. Under the discovery rule, the limitations period may start when the plaintiff knows, or should have known, of the injury. Horbach contended that the period began on February 5, 1991, when he learned of Shred Pax's wrongdoing. However, the court noted that Shred Pax had informed Horbach’s agent in April 1990 that the equipment was ready for inspection, yet Horbach waited over ten months to inspect it. The court found no justification for this delay and concluded that the limitations period began before September 1990, rendering the September 1995 fraud claim too late. Following the dismissal, Horbach sought to file a second amended complaint with additional allegations to revive the fraud claim and introduce a new conversion claim, but the court found this complaint equally unviable.

The court found Horbach's fraud claim unsubstantiated due to his failure to timely discover the alleged fraud regarding the pyrolysis equipment. Despite Horbach's argument that the equipment's complexity and his lack of technical expertise justified the delay, the court noted that the equipment's deficiencies were evident during an inspection in February 1991, which was several months after he could have reasonably inspected it. The court emphasized that qualified inspectors would have recognized the lack of an integrated system at the time of the inspection. Furthermore, Horbach's claim that he delayed inspection because he was awaiting modifications was refuted by evidence that Shred Pax completed these modifications by April 1990. The court also dismissed Horbach's reasoning of searching for a testing and installation site, stating that Shred Pax had indicated it would test the equipment at its own location if Horbach could not provide one within a specified timeframe. Consequently, the court deemed Horbach's ten-month postponement unjustifiable and dismissed the fraud claim. 

For the conversion claim, the court determined it was not viable because Horbach could not prove he retained ownership of the payments made to Shred Pax, as the purchase order allowed for periodic advance payments. The court clarified that Horbach's redress for the incomplete equipment should be through a breach of contract claim, not conversion. Additionally, under Illinois law, a conversion claim necessitates entitlement to a specific fund, which Horbach did not assert, as he claimed a general amount of money rather than specific coins or bills. Thus, the conversion claim was also dismissed.

Horbach challenges the district court's judgment on four grounds. First, he argues that a longer five-year limitations period for fraudulent concealment should apply to his breach of contract claim instead of the four-year period the court used. He claims that the Illinois legislature's provision for fraudulent concealment, 735 ILCS 5/13-215, should govern his case. Second, he asserts that if his breach of contract claim is timely, then his equitable claims should also be considered timely, and he contends the court incorrectly applied laches to dismiss these claims. Third, he maintains that it cannot be conclusively stated that he should have known of the defendants' alleged fraud earlier, and thus, his fraud claim should not have been dismissed as untimely. Lastly, Horbach claims that his complaint adequately presents a valid conversion claim.

Regarding the timeliness of the breach of contract claim, Horbach contends the district court misapplied the four-year limitations period, citing the Illinois Supreme Court's decision in Anderson, which interprets fraudulent concealment as applicable only when a defendant's actions deprive a plaintiff of a reasonable time to file suit. Horbach discovered the alleged fraud in February 1991, with three years remaining to file within the four-year limit, leading the court to conclude that he had sufficient time to act. Although Horbach does not dispute the interpretation of Anderson, he believes it is inconsistent with the statute's language and hopes the Illinois Supreme Court would reconsider its ruling. However, the court finds no reason to disregard Anderson, affirming that federal courts must adhere to state law as defined by the state’s highest court unless that law has been clearly modified. As such, the court holds that the Illinois Supreme Court's interpretation in Anderson is applicable, confirming that the statute does not apply when a plaintiff has timely discovered their injury.

Horbach argues that the Illinois Supreme Court's decision in Hermitage Corp. v. Contractors Adjustment Co. does not indicate a retreat from the precedent set in Anderson. In Hermitage, the court addressed the discovery rule, which delays the statute of limitations until a plaintiff is aware of their injury, countering the defendant's claim that the discovery rule should not extend beyond the injury date if there is still time to file a suit. The court referred to its earlier decision in Sharpe v. Jackson Park Hosp., which rejected the idea that Anderson's interpretation of the fraudulent concealment statute created an exception to the discovery rule. The Hermitage court reaffirmed that the discovery rule and the fraudulent concealment statute serve different functions, and Anderson's "reasonable time" rule applies only to fraudulent concealment cases, not to discovery rule cases, thus not relevant in Hermitage. 

Furthermore, the court's decision in Morris v. Margulis, where it applied the "reasonable time" rule, reinforces that there is no abandonment of Anderson. 

Regarding the timeliness of Horbach's equitable claims, the district court dismissed them due to laches, relying on the expiration of the statute of limitations for his breach of contract claim. While Horbach does not dispute the application of laches, he maintains that his breach of contract claim was timely. 

For the fraud claim, Horbach had five years from when he discovered or should have discovered the fraud to file suit. He argues that he did not discover the fraud until February 1991, following an inspection of the equipment. The court questioned whether he should have been aware of the injury by September 1990, given that he was informed the equipment was ready for testing in April 1990. While the district court suggested he should have discovered the fraud earlier through a simple inspection, Horbach contends that the complexity of the equipment and his lack of expertise meant that he could not determine whether the system met the specifications without actual testing, which he asserts he was not positioned to conduct before September 1990.

Horbach's allegations indicate that he should have discovered the injury related to Shred Pax's purported fraud before September 1990. Despite claiming the complexity of the pyrolysis system and his lack of expertise, the complaint reveals that Shred Pax's fraud was evident during an inspection by Horbach's agent, who found no complete system at the Portland facility and noted that the visible components did not meet specifications. The court concluded that Horbach's delay in inspecting the equipment was unreasonable given the circumstances, including Shred Pax's announcement of equipment completion and the ongoing storage fees, leading to the dismissal of the fraud claim as untimely.

Regarding the conversion claim, Horbach asserts that he deposited $56,800 with the defendants between April and September 1990 based on their representation that the equipment was complete. He claims that the equipment was not ready and that the defendants wrongfully refused to return his payment upon demand. The legal definition of conversion requires wrongful deprivation of property to which the party has a right of possession. A claim for conversion typically does not apply to money unless it can be identified as "specific chattel" and the plaintiff must demonstrate absolute ownership of the funds at all times, which must have been converted by the defendant.

The district court's dismissal of Horbach's conversion claim was upheld, as he could not demonstrate that he had an absolute right to the money paid to the defendants for the pyrolysis equipment. Although the payments could be viewed as specific chattel, Horbach's agreement with the defendants required him to make those payments in exchange for their promise to complete and store the equipment. Since the equipment was incomplete and did not meet specifications, there was a potential obligation for the defendants to return some or all of the payments. However, this did not establish that the money was unconditionally his, as the defendants' receipt of it was not unauthorized or wrongful—a necessary condition for a conversion claim. Consequently, the court affirmed the dismissal of Horbach's other claims, including breach of contract, rescission, constructive trust/unjust enrichment, and fraud. Notably, One Three Six did not participate in the appeal, and Horbach's additional claims regarding a stock purchase agreement and a new breach of contract claim related to equipment storage were not addressed in this appeal, with the latter being deemed barred by the statute of limitations.