In this appellate case, Structural Dynamics Research Corporation (SDRC) contested a district court's judgment awarding damages and prejudgment interest to H. Dale Seamons related to sales quota credits for a Boeing option to purchase SDRC's software. The district court, operating under 28 U.S.C. 1332, found ambiguity in a 1995 agreement concerning quota credits for 'Mega Deals' but ruled that the evidence did not demonstrate SDRC's obligation to provide credit to Seamons for the Boeing sale. The court also evaluated whether Seamons' entitlement to quota credits predated the agreement, concluding no forfeiture occurred upon signing. The appellate court, with jurisdiction under 28 U.S.C. 1291, agreed with the lower court's decision, highlighting the incorrect but harmless finding of ambiguity. It clarified that the contract specified quota credits for sales above $2.5 million and that the Mega Deals rider, affecting commission rates, did not apply to Seamons or quota credits. As SDRC failed to explicitly include such provisions, the contract was interpreted against them. Consequently, the appellate court affirmed the district court's judgment. The ruling is unpublished and non-citable within the circuit, per 9th Cir. R. 36-3, with Judge Rawlinson concurring in the result.

Legal Issues Addressed

Application of Contract Riders

Application: The Mega Deals rider was found not applicable to the quota credits or to Seamons as a District Manager, which should have been explicitly stated if intended.

Reasoning: Importantly, Seamons, as a District Manager, was not subject to the Mega Deals rider, which limited its application to specific employee roles.

Contract Ambiguity and Interpretation

Application: The appellate court found the district court's determination of ambiguity in the 1995 agreement to be incorrect but deemed it harmless in the overall decision.

Reasoning: The appellate court found the initial determination of ambiguity in the agreement to be incorrect but harmless.

Interpretation Against the Drafter

Application: The contract was construed against SDRC, as the drafter, leading to the conclusion that Seamons' quota credits were unaffected by the Mega Deals rider.

Reasoning: The court reasoned that if SDRC intended for the rider to apply to quota credits or to District Managers, it should have explicitly stated so.

Quota Credits Entitlement

Application: The court determined that quota credits related back to when Boeing exercised its option and that the 1995 agreement did not state a forfeiture of prior credits.

Reasoning: It determined that the credit related back to when Boeing exercised its option and that the 1995 agreement did not clearly state a forfeiture of prior credits.