This case involved a dispute between an employee and his employer regarding unpaid overtime compensation under the Fair Labor Standards Act (FLSA), specifically 29 U.S.C.A. § 207. The plaintiff, who worked for a ready-mixed concrete company, claimed overtime pay for hours worked beyond the standard 40-hour workweek without receiving the mandated overtime rate. The trial court ruled in favor of the plaintiff, awarding him $990.56, which included overtime compensation, liquidated damages, and attorney fees. The employer appealed, arguing that its operations were local and not subject to the FLSA, despite the concrete being used in interstate highway construction. The appellate court referenced the precedent set in Alstate Construction Co. v. Durkin, affirming that such activities fall under the FLSA as they are integral to interstate commerce. The court also addressed procedural aspects, highlighting that pleading defects not raised at trial are waived, and concluded that the complaint sufficiently established a claim for relief. The appellate court upheld the trial court's decision, affirming the applicability of the FLSA and the plaintiff's entitlement to overtime compensation.

Legal Issues Addressed

Fair Labor Standards Act Applicability

Application: The court determined that the plaintiff was covered by the FLSA as his employment involved producing goods for interstate commerce.

Reasoning: This employment qualifies as 'production of goods for commerce' under the Fair Labor Standards Act (FLSA).

Jurisdiction Under Interstate Commerce

Application: Activities related to the construction of infrastructure on interstate highways are integral to interstate commerce and fall under FLSA coverage.

Reasoning: The excerpt references the case of Alstate Construction Co. v. Durkin, where the Supreme Court upheld that employees involved in repairing and reconstructing interstate roads are covered by the FLSA, as such activities are integral to interstate commerce.

Overtime Compensation Requirements

Application: The plaintiff is entitled to overtime compensation at one and one-half times his regular pay for hours exceeding forty per week.

Reasoning: Consequently, the plaintiff is entitled to overtime compensation at one and one-half times his regular pay for hours exceeding forty per week, amounting to $395.28.

Pleading Sufficiency and Waiver of Defects

Application: Defects in pleading not raised in the trial court are waived, and a clear statement of facts suffices for liability claims under the Illinois Civil Practice Act.

Reasoning: The court referenced the Illinois Civil Practice Act, emphasizing that a clear statement of facts suffices for liability claims and that any pleading defects not raised in the trial court are waived.

Waiver of FLSA Provisions

Application: The defendant's claim of a waiver of FLSA provisions was disputed by the plaintiff and found unpersuasive by the court.

Reasoning: The defendant did not challenge the complaint's sufficiency in the trial court but denied FLSA applicability and claimed an agreement to waive its provisions, which the plaintiff disputed.