Narrative Opinion Summary
In this case, Bill Strong Enterprises, Inc. (BSE) contested a decision by the Armed Services Board of Contract Appeals (ASBCA), which denied recovery of consultant costs under FAR 31.205-33. BSE had contracted with the Department of the Army for housing renovations and sought equitable adjustments due to delays, incurring costs with Excell, Inc. for claim preparation. The ASBCA ruled these costs unallowable, deeming them related to claim prosecution. On appeal, the court reversed, clarifying that consultant costs for contract administration and negotiation are allowable, distinguishing them from costs for claim prosecution. The court found no formal CDA claim existed when the costs were incurred, thus they were not unallowable. The decision underscored the proper interpretation of 'claim' under FAR 33.201, emphasizing that costs intended to facilitate settlement rather than litigation are permissible. The case was remanded to assess the reasonableness and allocability of the costs. The ruling aligns with the regulatory framework, allowing recovery of costs that benefit contract performance and resolution without litigation.
Legal Issues Addressed
Allowability of Consultant Costs under FAR 31.205-33subscribe to see similar legal issues
Application: The court determined that consultant costs incurred for contract administration, rather than for prosecuting claims, are allowable under FAR 31.205-33.
Reasoning: BSE's engagement of Excell was primarily for contract administration and negotiation support, benefiting the Government, thus rendering the costs allowable under FAR 31.205-33.
Definition of 'Claim' under FAR 33.201subscribe to see similar legal issues
Application: The court found that no formal CDA claim existed at the time BSE incurred consultant costs, thus these costs were not related to prosecuting a claim against the Government.
Reasoning: The November 30, 1989 submission cannot be classified as a formal CDA claim because BSE did not request a final decision from the Contracting Officer (CO), and the parties had not reached a dispute stage by that date.
Distinction Between Contract Administration and Claim Prosecution Costssubscribe to see similar legal issues
Application: The court clarified that costs related to negotiations and contract administration are allowable, whereas costs incurred specifically for claim prosecution are not.
Reasoning: Costs incurred to further negotiations should generally be deemed allowable, even if negotiations fail and a claim is later submitted.
Impact of Contract Completion on Cost Allowabilitysubscribe to see similar legal issues
Application: The court held that costs incurred post-completion of contract work can be allowable if related to contract administration and necessary for settlement.
Reasoning: Furthermore, the Board erred in deeming the consulting costs unallowable on the grounds that they were incurred post-completion of contract work.
Review of Board Decisions under 41 U.S.C. Sec. 609(b)subscribe to see similar legal issues
Application: The court reviewed the Board's legal conclusions de novo, emphasizing that factual determinations are only conclusive if not erroneous.