R.J. Marshall, Inc. v. Freetown Sand & Gravel, Inc. (In re R.J. Marshall, Inc.)

Citations: 55 B.R. 199; 1985 Bankr. LEXIS 4949Docket: Bankruptcy No. 8500156; Adv. No. 850020

Court: District Court, D. Rhode Island; November 18, 1985; Federal District Court

Narrative Opinion Summary

In this contractual dispute, R.J. Marshall, Inc. sought to recover $10,278 in alleged overpayments from Freetown Sand, Gravel, Inc., a subcontractor on a housing project. Freetown failed to complete its obligations, leading Marshall to hire other subcontractors and incur backcharges totaling $24,250. Freetown contested these charges, asserting it could have completed the work for $3,254 and counterclaimed for $9,951 under the contract. The court found that the documentary evidence was incomplete and relied heavily on witness testimony. It concluded that Freetown should be backcharged $13,582 for reasonable expenses incurred by Marshall due to Freetown's failure to perform, including equipment rental and incomplete landscape work. Despite these backcharges, a balance of $390 was determined to be owed to Freetown. Marshall's claim for overpayments was denied, while Freetown's counterclaim was allowed. The court also disallowed several specific charges due to insufficient evidence. Ultimately, the court emphasized the need for credible substantiation of backcharges and found that the reasonable cost to complete Freetown's obligations was $13,582, leading to the final judgment that Marshall's claims were unfounded beyond this amount, and Freetown was entitled to a small remaining contract balance.

Legal Issues Addressed

Burden of Proof for Backcharges

Application: The party asserting backcharges must substantiate them with credible evidence to be deemed reasonable and allowable.

Reasoning: The court found the backcharges related to equipment rental, materials, and manpower, totaling $3,982, to be reasonable, as Freetown's equipment was inoperable during part of the project, necessitating Marshall to hire additional resources.

Contractual Backcharges and Deductions

Application: When a contractor fails to complete work, the hiring party may apply backcharges for additional costs incurred to finish the work.

Reasoning: The court determined that Freetown should be backcharged $13,582, leaving a balance of $390 owed to Freetown.

Contractual Obligations and Completion

Application: A subcontractor's failure to fulfill contractual obligations results in deductions from the contract price for incomplete or substandard work.

Reasoning: The findings conclude that Marshall is owed $9,200 for incomplete or substandard work, which includes a 15% overhead charge.

Counterclaims in Contract Disputes

Application: A subcontractor may assert a counterclaim for unpaid balances under the contract despite disputes over additional costs or incomplete work.

Reasoning: Freetown's counterclaim was allowed in the amount of $390.

Reasonableness of Additional Charges

Application: Charges such as overhead and handling fees must be substantiated and reasonable to be recoverable.

Reasoning: Marshall’s additional 10% charge for delays is disallowed as arbitrary, while a 15% handling charge on backcharges is deemed reasonable.