Delphi Petroleum v. Magellan Terminals Holdings, L.P.

Citation: Not availableDocket: N12C-02-302 FWW

Court: Superior Court of Delaware; July 10, 2018; Delaware; State Appellate Court

Original Court Document: View Document

Narrative Opinion Summary

In this case, Delphi Petroleum, Inc. initiated legal proceedings against Magellan Terminals Holdings L.P., alleging breach of contract and fraud due to overbilling for heating oil at a terminal facility. Following a bench trial and subsequent appeals, the Delaware Supreme Court affirmed most of the lower court's rulings, but remanded the case for recalibration of pre-judgment interest calculations. The court determined that Delphi was entitled to pre-judgment interest on overbilling, calculated at statutory rates from the time of payment. A dispute arose regarding the proper calculation method and interest related to claims not directly connected to the overbilling. The court ultimately accepted a revised calculation, aligning with accountant Donald Dahl's methodology, determining Magellan owed Delphi $442,883.92 in pre-judgment interest. The court's decision reflects a careful examination of statutory interest applications and ensures adherence to the Supreme Court's directive on determining the correct interest start date, thereby resolving the financial discrepancies between the parties.

Legal Issues Addressed

Breach of Contract and Fraud Allegations

Application: Delphi Petroleum, Inc. filed a lawsuit alleging breach of contract and fraud related to overcharges for heating oil by Magellan Terminals Holdings L.P.

Reasoning: Delphi Petroleum, Inc. filed a lawsuit against Magellan Terminals Holdings L.P. in February 2012, alleging breach of contract and fraud related to the operation of a marine terminal in Wilmington, Delaware.

Calculation of Pre-Judgment Interest

Application: The court had to determine the correct amount of pre-judgment interest owed based on overbilling data and statutory interest rates.

Reasoning: Delphi requested additional pre-judgment interest... while Magellan proposed a pre-judgment interest calculation of $325,064.93.

Dispute Over Pre-Judgment Interest Calculations

Application: A disagreement arose regarding the inclusion of interest on unrelated claims, which was resolved by adopting a mutually agreed calculation.

Reasoning: Magellan acknowledged this error and agreed with Dahl's figure. The court denied Delphi's motion to file a brief but allowed a letter submission related to the final request.

Recalibration of Pre-Judgment Interest

Application: The Delaware Supreme Court remanded the case for recalibration of pre-judgment interest due to overcharges for fuel, impacting the damages awarded.

Reasoning: Following appeals, the Delaware Supreme Court upheld most of the lower court's decisions but reversed a $2,500 fraud claim award to Delphi and remanded the case for a recalibration of pre-judgment interest due to overcharges for fuel.

Start Date for Pre-Judgment Interest

Application: The Supreme Court found that the start date for pre-judgment interest should be from when Delphi paid the overcharges.

Reasoning: The Supreme Court agreed, stating that interest should run from when Delphi paid the overcharges, and remanded the case for determining appropriate interest dates.

Statutory Rate Application

Application: The court determined the application of statutory interest rates to calculate interest on overbilling.

Reasoning: The Court determined Delphi was entitled to interest on the total overbilling of $536,150.00 at the statutory rate starting September 25, 2013...