An appeal was filed challenging the Lucas County Court of Common Pleas' summary judgment in favor of Anchor Pointe Marina, against appellants who sought damages for their boat, loss of dock space value, and personal injury. The disputes arose from a winter boat storage agreement, with appellants alleging a bailment was formed when the marina assured care of their boat. The trial court granted summary judgment for appellee, validating the exculpatory clauses in the storage agreement and denying the existence of a bailment. It also ruled that the personal injury claim failed as the risk was open and obvious. On appeal, the court found errors in excluding certain statements as hearsay and in determining the modification of the agreement, leading to a partial reversal. The court upheld the summary judgment on the personal injury claim but remanded the case for further proceedings on the claims related to boat damage and dock space value. The decision acknowledged genuine issues of material fact regarding the modification of the agreement and whether the marina's actions affected the dock space's value.

Legal Issues Addressed

Bailment and Modification of Agreements

Application: Appellants argued that a bailment agreement was formed or modified when the marina's representatives allegedly assured them that the boat would be taken care of, but the trial court found no admissible evidence of such modification.

Reasoning: The court then examines whether the parties modified the 'Winter Boat Storage Worksheet' to make appellee responsible for removing the drain plugs.

Exculpatory Clauses in Contracts

Application: The court evaluated whether the exculpatory clauses in the 'Winter Boat Storage Agreement' and 'Winter Boat Storage Worksheet' were enforceable, ultimately finding them valid unless proven unconscionable or against public policy.

Reasoning: Although the appellants initially claimed the clauses were unenforceable based on public policy rather than unconscionability, the trial court found the disclaimers enforceable.

Hearsay and Admissions of a Party Opponent

Application: The court determined that statements made by marina employees could be considered admissions of a party opponent, not hearsay, and should be admissible.

Reasoning: Thus, the court finds the statements are not hearsay, and the trial court erred in excluding them.

Open and Obvious Doctrine in Premises Liability

Application: The court upheld the application of the open and obvious doctrine, finding that the marina had no duty to protect Mr. Fuller from a hazard he acknowledged knowing about.

Reasoning: Mr. Fuller acknowledged awareness of the conduit’s presence, indicating that he had actual knowledge of the hazard.

Summary Judgment Standard

Application: The appellate court reviewed the trial court's summary judgment ruling de novo, assessing whether genuine issues of material fact existed for trial.

Reasoning: Summary judgment is appropriate when no genuine issue of material fact exists, the moving party is entitled to judgment as a matter of law, and reasonable minds can only reach one conclusion adverse to the nonmoving party.