Vocational Bd. of Edn. v. Peterson Constr.

Citations: 716 N.E.2d 1210; 129 Ohio App. 3d 58; 1998 Ohio App. LEXIS 3207Docket: Nos. CA97-05-024, CA97-05-026

Court: Ohio Court of Appeals; July 13, 1998; Ohio; State Appellate Court

Narrative Opinion Summary

In a case involving the Central Ohio Joint Vocational School District Board of Education, Peterson Construction Company, and George J. Igel and Company, the Board appealed a jury verdict concerning the expansion of the Tolles Technical Center. The core legal issues revolved around contract interpretation and the applicability of the Spearin doctrine. The Board initially sued Peterson and Dunbar Geotechnical Engineers for breach of contract and negligence, but claims against Dunbar and negligence claims were dismissed. The jury found against the Board, awarding Peterson damages. On appeal, the Board contested the trial court's decision to allow the jury to interpret a crucial contract provision and the jury instructions regarding the Spearin doctrine. The court found the term 'FULL DEPTH' in the contract ambiguous, justified as a jury question, and upheld the jury's interpretation. The Spearin doctrine's applicability was affirmed despite the Board's arguments to the contrary, including an express warranty claim. The judgment was affirmed, with Peterson's indemnification claim against Igel also addressed. The case underscores the complexities of contract interpretation and the interplay between express and implied contractual obligations.

Legal Issues Addressed

Breach of Contract and Negligence Claims

Application: The Board sued Dunbar and Peterson for breach of contract and negligence, but claims against Dunbar were dismissed and negligence claims were not pursued.

Reasoning: On July 24, 1995, the Board sued Dunbar and Peterson for breach of contract and negligence. Peterson counterclaimed against the Board and cross-claimed against Dunbar. Before the trial, claims against Dunbar were dismissed, as were the negligence claims.

Change Order and Contractual Modifications

Application: A change order modified the contract, transferring excavation responsibility to Dunbar and adding requirements for additional stone base material.

Reasoning: The existence of a change order implies a modification of the contract terms, allowing Dunbar discretion over soil excavation depth prior to adding stone.

Express Warranty and Contractual Obligations

Application: The Board's argument that express warranties by Peterson override the Spearin doctrine was rejected as the contract was open to interpretation.

Reasoning: The Board argues that the Spearin doctrine, which implies a warranty, is overridden by express warranties from Peterson. ... Because the contract is open to interpretation, the express warranty exception does not apply.

Interpretation of Contract Provisions

Application: The case hinged on the interpretation of Section 2100-3.02(A) of the contract, where the term 'FULL DEPTH' was deemed ambiguous, thus a proper question for the jury.

Reasoning: The Board argues that the phrase 'FULL DEPTH' unambiguously requires the complete removal of organic soil. In contrast, the appellees assert that the provision is ambiguous and that the interpretation of 'FULL DEPTH' depends on the soils engineer's directions.

Spearin Doctrine

Application: The court found that the Spearin doctrine, which implies an owner's warranty of plan accuracy, was applicable despite Board's arguments to the contrary.

Reasoning: The court found the disclaimer of liability exception inapplicable, arguing that the contract terms were not clear and unambiguous and suggesting that the excavation was to be executed under the direction of Ben Backus, the soils engineer.