Wilson v. Los Angeles County Metropolitan Transportation Authority

Docket: S077461

Court: California Supreme Court; June 12, 2000; California; State Supreme Court

EnglishEspañolSimplified EnglishEspañol Fácil
In the Supreme Court of California case KAJIMA/RAY WILSON v. LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY, the court examined whether a lowest responsible bidder, wrongfully denied a public contract, can seek monetary damages from the public entity, and if such damages encompass bid preparation costs and lost profits. The court determined that while bid preparation costs are recoverable under promissory estoppel, lost profits are not. The case arose from a bid solicitation by the MTA for the construction of the Red Line Hollywood/Highland station, where Kajima successfully protested the awarding of the contract to Tutor-Saliba due to the latter's failure to meet the Disadvantaged Business Enterprise (DBE) goals. After rejecting all bids in the first solicitation, the MTA later issued a new bid request with a minimum DBE requirement. Despite Kajima submitting the lowest bid, the contract was awarded to Tutor-Saliba, which met the DBE criteria. Kajima's protest was based on an unwritten MTA policy that disadvantaged its bid by classifying an identified trucking entity as a broker rather than a subcontractor, impacting its DBE credit. Kajima ultimately filed suit seeking various damages totaling over $3 million, including bid expenses and overhead costs, plus prejudgment interest.

Following a bench trial, the court granted a peremptory writ of mandate requiring the MTA to discontinue its 5 percent broker policy concerning DBE credits, mandating a proper evaluation of subcontracted work. Kajima was awarded a total judgment of $923,921.74, which included $44,869 for round 2 bid expenses, $89,223 for round 2 bid protest expenses, $300,000 for unabsorbed overhead, $350,000 for lost profits, and $139,829.74 in prejudgment interest. The Court of Appeal upheld the trial court's decision, deeming MTA's application of the 5 percent policy as arbitrary, in violation of federal regulations, and an abuse of discretion—this ruling was not contested by MTA. The appellate court also affirmed the trial court's discretion in awarding lost profits under the doctrine of promissory estoppel, emphasizing that recovery of damages, including lost profits, should be evaluated on a case-by-case basis. MTA waived its right to contest the overhead costs on appeal. The court's denial of MTA's petition for rehearing led to a review regarding the cause of action for monetary damages for the lowest responsible bidder wrongfully denied a public contract, specifically focusing on Kajima's bid preparation costs and lost profits, while the issues of bid protest costs and overhead costs were waived by MTA. The excerpt further explains the doctrine of promissory estoppel in California law, which holds that a promise inducing action is binding if the enforcement is necessary to avoid injustice. This principle was illustrated in the case of Drennan v. Star Paving Co., where a subcontractor's bid was enforced due to the general contractor's reliance on it, even in the absence of a formal contract.

Argo Construction Company, Inc. (Argo) sought a mandate to have a management contract awarded to Swinerton set aside, asserting it was the lowest responsible bidder wrongfully denied the contract. The court agreed with Argo and remanded the case. On appeal, it was concluded that a misaward of a public works contract to a party other than the lowest responsible bidder does not provide a tort cause of action to the lowest bidder. However, Swinerton was allowed to pursue damages under promissory estoppel. The court emphasized that the Authority's promise to award the contract to the lowest responsible bidder created a reliance interest for Argo that could not be disregarded. The civic center authority's argument that Argo could not claim promissory estoppel due to the nature of public bidding was rejected; the court asserted that such a stance would undermine the integrity of the bidding process. The court noted that enforcing the promise was necessary to avoid injustice and promote public interest, as awarding damages to the lowest responsible bidder would deter future misconduct by public entities. Argo's recovery under promissory estoppel might be limited to expenses incurred during the bidding process. Ultimately, Argo presented sufficient facts for a cause of action in promissory estoppel against public entities, with the specifics of recovery to be determined at trial, including considerations for Swinerton's potential quantum meruit recovery.

In *Universal By-Products, Inc. v. City of Modesto*, the court denied recovery under promissory estoppel to a disappointed bidder since the public entity exercised its right to reject all bids. The court emphasized that the appellant, as an experienced business entity, accepted the risk of such rejection as part of the bidding process, which includes the costs of bid preparation. Subsequent cases, including *Pacific Architects Collaborative* and *Monterey Mechanical Co.*, affirmed that no recovery for bid preparation costs is available when all bids are rejected. The *Monterey Mechanical* case specifically ruled that damages would be inadequate since the district was immune from tort liability, and any potential promissory estoppel damages would only cover bid preparation costs. 

The analysis also addresses whether a lowest responsible bidder not awarded a contract can pursue monetary damages against a public entity after injunctive relief is no longer available. The MTA contends that such a bidder lacks a cause of action for damages, while Kajima disputes this assertion. California's competitive bidding laws do not explicitly grant a remedy for damages to a wrongfully denied lowest responsible bidder, leading to speculation that the Legislature either chose not to provide such a remedy or assumed recovery could be sought through promissory estoppel. Historically, courts have allowed disappointed bidders to seek writs of mandate to set aside contracts, a remedy not codified by the Legislature. Additionally, claims for monetary damages against the MTA are governed by specific provisions of the Government Code and relevant statutes.

Government Code section 811 defines "Law" to include both statutory and decisional law from state and federal courts. Section 814 clarifies that contracts are not affected by this part, indicating that a disappointed bidder may seek monetary relief if a valid theory exists. Allowing such recovery promotes the objectives of competitive bidding laws by encouraging legitimate challenges to public contracts and discouraging government misconduct. Competitive bidding statutes aim to foster competition, prevent favoritism and corruption, and ensure the best prices for public contracts.

In the case of Kajima, the parties acknowledge that monetary relief could be pursued under a promissory estoppel theory. This theory applies when a public entity solicits bids and implies that the contract will be awarded to the lowest responsible bidder. Kajima incurred $44,869 in bid preparation costs based on this representation. If awarded to a higher bidder despite being the lowest responsible bidder, the elements for a promissory estoppel claim appear satisfied, though the MTA does not contest this point. However, the theory of promissory estoppel is not a perfect fit as it was designed to address situations where a party relies on a promise without contractual protection.

In the context of measuring damages, the question arises whether a public entity can be liable for bid preparation costs and lost profits due to a misawarded contract. The law allows for recovery of bid preparation costs incurred in reliance on the expectation of being awarded the contract, while lost profits are not recoverable. Due to the MTA's discretion to reject all bids and the uncertainties inherent in the bidding process, only the bid preparation costs are considered reasonable and recoverable.

The lowest bid may often be unprofitable due to potential miscalculations or unexpected cost increases, which can diminish or eliminate the bidder's profit margin. Awarding the plaintiff profits it would have earned appears disproportionate to actual losses and speculative in nature, possibly placing Kajima in a better position than had it performed the contract. According to the Restatement of Contracts, damages should not benefit the promisee beyond what performance would have provided unless unjust enrichment of the promisor occurs. Kajima contends that without recoverable lost profits, there would be little motivation for disappointed bidders to pursue valid claims or participate in public works bidding. However, numerous cases demonstrate that significant monetary damages are not necessary for bidders to protect the competitive bidding process. The rarity of lost profit awards further undermines Kajima's argument regarding bidder participation. Furthermore, it is established that no equitable principle can be applied against governmental bodies if it undermines a policy designed to protect the public. Competitive bidding laws are intended to benefit property holders and taxpayers, not to enrich bidders, and should be interpreted to serve the public interest. Allowing disappointed bidders to recover lost profits may unfairly penalize taxpayers and provide unwarranted windfalls to bidders for efforts not made and risks not taken. This recovery could also lead to frivolous litigation, straining public resources.

Prudence is essential when courts determine damages remedies in areas governed by extensive statutory frameworks. Kajima argues that awarding lost profits to a disappointed bidder would not result in double payments to the public because payments made to the successful bidder under an allegedly void contract could be recouped by the agency. However, the validity of the contract between MTA and Tutor-Saliba and the feasibility of recouping payments are not under consideration, making it inappropriate to base a damages remedy on speculation.

Kajima also contends that contracts between public entities and private parties are subject to the same legal principles as private contracts. Nonetheless, Kajima lacks a direct contract with MTA and may only seek damages through the equitable doctrine of promissory estoppel. When assessing the remedy that "justice requires," it is vital for the court to consider the potential social implications. Awarding lost profits for denied contracts could financially burden the public due to governmental negligence.

Most jurisdictions align with the principle that competitive bidding laws serve public interests rather than private contractors, often denying disappointed bidders a cause of action for damages. While bidders may challenge the rejection of their bids to ensure public officials fulfill their duties, this does not create a right for bidders to claim damages from public agencies. Many jurisdictions permit recovery of bid preparation and protest costs, but not lost profits, as this distinction encourages legitimate challenges to public contract awards while protecting public funds from additional burdens. Courts are generally reluctant to grant lost profits without an existing contract.

Lost profits have been recognized as a potential measure of damages in cases of bad faith, although only two cases have awarded such damages to disappointed bidders: *City of Durant v. Laws Construction Co., Inc.* and *Bradford v. Bigelow, Inc.* The Court of Appeal's stance on allowing disappointed bidders to recover lost profits is a minority viewpoint. The Court relied on two California cases—*C. K. Engineering Contractors v. Amber Steel Co.* and *Signal Hill Aviation Co. v. Stroppe*—which involved disputes between private parties and did not address the damages issue in the context of public contracts.

In *C. K. Engineering*, the court ruled that a promissory estoppel action was equitable, thus not warranting a jury trial, while in *Signal Hill*, the court affirmed an award of profits based on theories of promissory estoppel and constructive trust after a corporate officer reneged on a lease assignment. These cases are deemed irrelevant for assessing damages in public works contexts.

The judgment of the Court of Appeal is reversed, and the case is remanded for proceedings consistent with the opinion. The document notes that the most effective enforcement of competitive bidding laws typically involves injunctions to uphold the contract award to the lowest responsible bidder. However, practical delays may result in contracts being performed before legal relief can be granted, raising questions about monetary relief and the appropriate measure of damages. Disappointed bidders are acknowledged to have no tort or breach of contract claims against public agencies for wrongful contract awards, and remedies may be more appropriately governed by statutes in some jurisdictions.

An unsuccessful bidder lacks standing to claim monetary damages, as established in Lawrence Brunoli, Inc. v. Town of Branford, aligning with municipal bidding statutes aimed at protecting public interest. Several cases reinforce this principle: Sutter Bros. Construction Co. v. City of Leavenworth indicates no cause of action for damages if the action is initiated after contract award and completion of work; Gulf Oil Corp. v. Clark County emphasizes that the lowest bidder cannot seek damages if injunctive relief is not pursued diligently; and Stride Contracting Corp. v. Bd. of Contract and Supply of the City of Yonkers similarly affirms that the lowest responsible bidder is limited to seeking contract award rather than damages. M.A. Stephen Construction Co. Inc. v. Borough of Rumson reiterates that a lowest responsible bidder is not entitled to damages if bids are rejected contrary to statute.

Various state statutes provide limited remedies for protesting bidders, often allowing recovery of reasonable bid preparation costs rather than full damages. For instance, Alaska, Arkansas, Colorado, Hawaii, Louisiana, Maryland, Minnesota, South Carolina, and Utah statutes outline scenarios where a successful protest may entitle the bidder to recover costs associated with bid preparation but exclude attorney's fees. These provisions highlight a consistent legislative trend toward limiting financial recovery for unsuccessful bidders in the context of municipal contracts.

The Board may award reasonable costs for bid or proposal preparation and expenses related to pursuing a protest, excluding legal fees, if it determines the District government's actions were arbitrary or capricious. Relevant case law supports this position, indicating that unsuccessful bidders cannot recover lost profits due to the absence of a contract but may recover bid preparation expenses based on an implied promise from the government to fairly consider bids. Notable cases include Heyer Products Co. v. United States, which establishes that arbitrary government conduct allows for recovery of bid costs, and Keco Industries, Inc. v. United States, which extends this principle. Other cases, such as Planning, Design Solutions v. City of Sante Fe and City of Atlanta v. J.A. Jones Construction Co., reinforce the right to recover bid preparation costs while denying lost profits. Similarly, Telephone Associates, Inc. v. St. Louis County Bd. allows for the recovery of bid preparation costs and reasonable attorney fees, but not lost profits. Additional cases, including Owen of Georgia, Inc. v. Shelby County and Court Street Steak House, Inc. v. County of Tazewell, affirm the general consensus against recovering lost profits while permitting recovery of bid preparation expenses. Neilsen and Co. v. Cassia and Twin Falls County Joint Class A School District recognizes recovery of bid preparation costs for breach of an implied contract concerning bid consideration.