Richard A. Boddicker appeals a summary judgment favoring Suss Pontiac-GMC, Inc. from the Colorado Court of Appeals. The underlying dispute involves a lease agreement where Suss had the option to purchase property from Boddicker. The contract stipulated that Suss could exercise this option by notifying Boddicker by certified mail, with a deadline of June 1, 2006. Suss sent notice of intent to purchase via first-class mail on May 25, 2006, which Boddicker acknowledged receiving but later declined to honor the option, claiming the notice was not sent as per the contract requirements.

Suss initiated a lawsuit for specific performance of the purchase option, while Boddicker countered with a claim of default on rent payments. Both parties filed for summary judgment, which the trial court granted to Suss, concluding that the option had been properly exercised.

The appellate court affirmed the trial court's ruling. It analyzed whether the court should enforce the option despite the method of delivery differing from the contract stipulation. The majority of courts support enforcement if the alternative method provides actual notice. The court identified three rationales for this approach, with the first being that the alternative delivery could fulfill the parties' intent. The court emphasized that strict adherence to notice provisions is often not enforced when the substance of the agreement is unaffected, validating the trial court's decision.

In contract law, the language used by an offeror regarding methods of acceptance may be interpreted as suggesting a satisfactory method rather than imposing a strict requirement to follow that method. For example, if an offer specifies that acceptance must be by return mail, an acceptance sent by a different, timely means can still create a contract upon its arrival. This approach is particularly relevant in the context of option contracts, where both parties shape the terms through negotiation. Courts must consider the intent and reasonable expectations of both parties rather than solely the offeror's intentions.

The intent behind requiring notice via certified or registered mail is primarily to avoid disputes over timeliness and delivery. Courts have recognized that alternative methods of notice can be acceptable if they effectively achieve the same purpose as the specified method, even under jurisdictions that advocate for strict compliance. For instance, sending notice via regular mail may suffice if it is proven to be timely received. However, alternative delivery methods that do not clarify issues of timeliness and receipt are generally not permitted. This principle is supported by various case law examples illustrating that as long as the alternative method fulfills the intended function of the original requirement, it can be considered valid for contract enforcement.

Compliance with the lease agreement's provisions would have eliminated disputes regarding the timely sending and receipt of notice. In prior cases, the use of ordinary mail was deemed insufficient when the recipient did not receive the correspondence. The parties in the current case did not emphasize the delivery method, indicating a reasonable intent to prevent disputes regarding timeliness and receipt. The court highlighted that while strict compliance with certain terms is necessary, it is not required for delivery methods when the alternative achieves the same benefit. Suss's use of first-class mail effectively exercised the option and complied with the contract's intent. Boddicker's claim that Suss's notice constituted a counteroffer was refuted based on the letter's language, affirming that interpretation of written documents is a legal question. Both parties sought appellate attorney fees under a lease provision; however, Boddicker's request was denied, and Suss, as the prevailing party, was awarded reasonable attorney fees incurred in the appeal. The judgment was affirmed, and the case was remanded for the trial court to determine Suss's attorney fees.