BGW Associates, Inc. v. Valley Broadcasting Co.

Citations: 532 F. Supp. 1112; 1981 U.S. Dist. LEXIS 15278Docket: 80 Civ. 6013(RWS)

Court: District Court, S.D. New York; October 19, 1981; Federal District Court

Narrative Opinion Summary

In a breach of contract case between BGW Associates, Inc., a Connecticut consulting firm, and Valley Broadcasting Company, a Nevada corporation, the United States District Court for the Southern District of New York addressed several legal issues. BGW claimed outstanding payments under a consulting contract, while Valley contended the contract was unenforceable due to unconscionability, duress, and fraudulent inducement. The court focused on the unconscionability claim, analyzing factors such as bargaining power and experience. Despite Valley's inexperience in television operations, the court found no evidence of an unfair bargaining process or terms excessively favoring BGW, noting the sophisticated nature of both parties and the successful outcomes of BGW's services. The jury's special verdict favored BGW, granting them $145,060.12, and the court upheld this decision, dismissing Valley's claims of fraudulent inducement and duress. The ruling emphasized Valley's voluntary engagement with the contract and lack of evidence supporting the excessive nature of BGW's fees. Consequently, the court affirmed the enforceability of the contract and BGW's entitlement to the remaining payments.

Legal Issues Addressed

Breach of Contract Claims

Application: BGW Associates successfully claimed the remaining payments under the second consulting contract, which Valley Broadcasting Company terminated prematurely.

Reasoning: BGW sought to recover the remaining $144,000 due and $1,060.12 in expenses, while Valley countered with claims of duress, fraudulent inducement, material breach by BGW, entitlement to set-off, and a defense of unconscionability.

Duress in Contract Law

Application: The jury found that Valley Broadcasting Company did not sign the contract under duress, supporting the enforceability of the contract terms.

Reasoning: Valley's voluntary decision to enter into the second contract with awareness of its implications and the jury's finding that it was not signed under duress reinforced this conclusion.

Fraudulent Inducement in Contract Formation

Application: The court dismissed Valley's claim of fraudulent inducement, supporting the jury's special verdict in favor of BGW Associates.

Reasoning: The court dismissed the claim of fraudulent inducement and accepted a jury's special verdict favoring BGW for $145,060.12.

Unconscionability in Contract Law

Application: The court determined that the consulting contract was not unconscionable, as Valley Broadcasting Company had meaningful choice and the terms were not excessively favorable to BGW Associates.

Reasoning: The court concluded that the contract was not unconscionable.