You are viewing a free summary from Descrybe.ai. For citation checking, legal issue analysis, and other advanced tools, explore our Legal Research Toolkit — not free, but close.

Dynegy Midwest Generation, Inc. v. Federal Energy Regulatory Commission

Citations: 633 F.3d 1122; 394 U.S. App. D.C. 225; 2011 U.S. App. LEXIS 3183; 2011 WL 476614Docket: 09-1306, 09-1308

Court: Court of Appeals for the D.C. Circuit; February 11, 2011; Federal Appellate Court

Original Court Document: View Document

Narrative Opinion Summary

The case involves a challenge by operators of power generation facilities against Federal Energy Regulatory Commission (FERC) orders permitting an amendment to the tariff of the Midwest Independent System Operator (ISO). The amendment introduced Schedule 2-A, which allows transmission owners to opt-out of compensating generators for reactive power within a defined deadband, leading to varied compensation across different zones. The petitioners argued that this led to undue discrimination, violating Section 205(b) of the Federal Power Act (FPA), and that transmission owners lacked authority under Section 205 to file the new tariff. The court sided with the petitioners on the discrimination claim, finding that the tariff amendment created competitive disparities among generators, thus violating non-discrimination principles. However, the court upheld FERC's interpretation regarding the authority of transmission owners to file the tariff under an ambiguous Settlement Agreement. Ultimately, the court granted the petitioners' challenge on the discrimination issue, vacating the approval of Schedule 2-A, while rejecting their claim concerning the authority to file the tariff. The decision underscores the importance of ensuring competitive fairness and non-discriminatory access in electricity markets.

Legal Issues Addressed

Authority to File Tariff under Federal Power Act Section 205

Application: The court upheld FERC's interpretation that the Settlement Agreement allows transmission owners to submit filings regarding ancillary service rates, including Schedule 2-A, contrary to the petitioners' argument.

Reasoning: The Commission's interpretation that the Settlement allows transmission owners to file Schedule 2-A is deemed reasonable.

Collateral Attack and Timeliness under Federal Power Act Section 313(b)

Application: The court determined that the petitioners' challenge was not an impermissible collateral attack because they did not have a reasonable basis to perceive prior orders as FERC asserted.

Reasoning: The court found that the petitioners did not meet the criteria for a collateral attack, indicating they lacked a reasonable basis to perceive the orders in the manner FERC asserted.

Comparability Requirement in Electricity Tariffs

Application: FERC's failure to demonstrate that comparability adequately addressed competitive disparities among zones was a key factor in the court's rejection of Schedule 2-A's approval.

Reasoning: The Commission failed to provide evidence from Orders Nos. 2003 and 2003-A supporting its current interpretation of the comparability requirement and the FPA’s anti-discrimination provisions.

Discrimination under Federal Power Act Section 205(b)

Application: The court found that the compensation structure allowing transmission owners to opt out of compensating for reactive power within a deadband leads to arbitrary competitive disparities among generators, violating the non-discrimination provisions.

Reasoning: The discrimination claim argues that a compensation system permitting transmission owners to decide on reactive power compensation within a deadband leads to arbitrary competitive disparities among generators across zones, violating Section 205(b) of the FPA.