You are viewing a free summary from Descrybe.ai. For citation checking, legal issue analysis, and other advanced tools, explore our Legal Research Toolkit — not free, but close.

Brigham Young University v. Paulsen Construction Co.

Citations: 744 P.2d 1370; 42 Educ. L. Rep. 982; 68 Utah Adv. Rep. 5; 1987 Utah LEXIS 800Docket: 19638

Court: Utah Supreme Court; October 27, 1987; Utah; State Supreme Court

Narrative Opinion Summary

In this case, the Supreme Court of Utah addressed the statute of limitations applicable to Brigham Young University's (BYU) claims against Paulsen Construction Company and Christiansen Brothers Associates, Inc. BYU alleged negligent supervision regarding non-compliant pipe insulation, which led to pipe corrosion. The district court had dismissed BYU's claims as time-barred under a three-year statute for property injury. However, the Supreme Court found that the correct statute of limitations was six years for breach of written contracts, under Utah Code Ann. § 78-12-23(2). The court held that BYU's claims against Christiansen were timely as they were based on written agreements. Conversely, the claims against Paulsen were affirmed as barred, given BYU's awareness of the issues more than three years prior to the expiration of the limitations period, which made the discovery rule inapplicable. The court clarified that the distinction between tort and contract claims was crucial, as BYU's claims arose from contractual breaches rather than tortious property injury. Ultimately, the dismissal of claims against Paulsen was upheld, while the dismissal against Christiansen was reversed, allowing BYU to proceed with claims related to Christiansen's contractual obligations.

Legal Issues Addressed

Accrual of Construction Contract Claims

Application: Claims for breach of construction contracts typically accrue at the completion of construction, not at the discovery of defects.

Reasoning: Research indicates that while the discovery rule applies to professional malpractice cases... it is generally not applied to construction contract breaches, which typically accrue at the completion of construction.

Application of the Discovery Rule

Application: The discovery rule, which can toll the statute of limitations until the plaintiff discovers the cause of action, was deemed inapplicable because BYU knew the relevant facts more than three years before the limitation period expired.

Reasoning: However, Utah law generally stipulates that ignorance of a cause of action does not stop the statute of limitations from running.

Distinction Between Tort and Contract Claims

Application: The court clarified that BYU's claims did not fall under the three-year limitation for property injury but under the six-year limitation for breach-of-contract claims.

Reasoning: The district court incorrectly applied the three-year limitation from section 78-12-26(1), reasoning that the claims were for property injury.

Negligence in Performance of Contractual Duty

Application: BYU's assertion that Paulsen's negligence constitutes a tort does not change the case's nature, as negligent performance of a contractual duty remains a breach of contract.

Reasoning: Furthermore, BYU's assertion that Paulsen's negligence constitutes a tort does not alter the nature of the case, as negligent performance of a contractual duty is still a breach of contract.

Statute of Limitations for Breach of Contract

Application: The court determined that BYU's claims were based on written contracts, thereby subject to a six-year statute of limitations under Utah Code Ann. § 78-12-23(2).

Reasoning: BYU's claims against them are based on alleged breaches of contract, which fall under the six-year limitations period outlined in section 78-12-23.