You are viewing a free summary from Descrybe.ai. For citation checking, legal issue analysis, and other advanced tools, explore our Legal Research Toolkit — not free, but close.

Blue Tee Corp. v. CDI Contractors, Inc.

Citations: 529 N.W.2d 16; 247 Neb. 397; 1995 Neb. LEXIS 34Docket: S-93-411

Court: Nebraska Supreme Court; February 9, 1995; Nebraska; State Supreme Court

Narrative Opinion Summary

The case involves Blue Tee Corporation's attempt to foreclose on a bond under the Nebraska Construction Lien Act for structural steel supplied to Northwestern Steel Supply Co., which fabricated the steel for CDI Contractors, Inc., the general contractor of a construction project. The primary legal issue centered on whether Northwestern acted as a subcontractor or a materialman, as this classification would determine Blue Tee's eligibility for lien protection. The district court initially dismissed Blue Tee's claim, classifying Northwestern as a materialman. However, upon appeal, the Supreme Court of Nebraska reversed this decision, concluding that Northwestern's substantial labor contribution in fabricating steel constituted subcontractor status, thereby entitling Blue Tee to lien protection. The court also addressed the issue of prejudgment interest, ruling that Blue Tee's claim was unliquidated due to a reasonable dispute over Northwestern's classification, thus barring interest. The case was remanded with instructions to enter judgment in favor of Blue Tee for its foreclosure proceeding.

Legal Issues Addressed

Mechanic's or Construction Lien - Equitable Action and Burden of Proof

Application: The appellate court reviewed the classification de novo, emphasizing that the claimant must prove their entitlement to protection under the statute.

Reasoning: An action for foreclosure of a mechanic's or construction lien is based in equity, with appellate courts reviewing factual questions de novo...The claimant bears the burden of proving that the statute protects them.

Nebraska Construction Lien Act - Subcontractor vs. Materialman Classification

Application: The court assessed whether Northwestern Steel Supply Co. was a subcontractor or a materialman to determine if Blue Tee Corporation could claim lien protection.

Reasoning: The critical issue was whether Northwestern was classified as a subcontractor or a materialman. If deemed a subcontractor, Blue Tee could claim lien protection as a supplier; if a materialman, it could not.

Prejudgment Interest - Liquidated vs. Unliquidated Claims

Application: The court found Blue Tee's claim unliquidated due to reasonable controversy over Northwestern's classification, precluding prejudgment interest.

Reasoning: Prejudgment interest is only applicable when a claim is liquidated, meaning there are no disputes regarding the right to recover or the recovery amount. The dispute over whether Northwestern was a subcontractor indicates a reasonable controversy, rendering Blue Tee's claim unliquidated and barring an award of prejudgment interest.