You are viewing a free summary from Descrybe.ai. For citation checking, legal issue analysis, and other advanced tools, explore our Legal Research Toolkit — not free, but close.

Cr Perry Const., Inc. v. Cb Gibson & Assoc., Inc.

Citation: 523 So. 2d 1221Docket: 87-254

Court: District Court of Appeal of Florida; April 12, 1988; Florida; State Appellate Court

Narrative Opinion Summary

In a construction contract dispute, Charles R. Perry Construction, Inc. appealed a judgment favoring C. Barry Gibson Associates, involving the completion and payment for drywall installation in a hotel project. Perry subcontracted Gibson, who completed the work and sought the remaining balance of $55,914.70. Perry's defenses included an oral agreement deferring payment, alleged defects, and back charges. The trial court upheld Gibson's claim, finding that Gibson installed the STO exterior insulation system per approved specifications and that any defects did not breach its warranty obligations. On appeal, Perry argued that Gibson warranted defect-free materials and that payment was contingent upon approval from the architect and owner. The court found these payment conditions ambiguous, favoring Gibson's interpretation. Additionally, substantial evidence supported the trial court's findings on caulked joints, denying Perry's offset claim. Judges Booth and Wigginton concurred, affirming the trial court's ruling in Gibson's favor, awarding the unpaid balance plus interest.

Legal Issues Addressed

Back Charges and Offset Claims in Construction Disputes

Application: The appellant's claim for offset due to alleged defects, such as caulked joints, was denied as the court found substantial evidence supporting Gibson’s performance.

Reasoning: The trial court's determination regarding the caulked joints was also contested by the appellant, who sought an offset for back charges.

Construction Contractual Obligations and Warranty

Application: The court evaluated whether Gibson fulfilled its contractual obligations under the warranty clause and determined Gibson had installed the STO system according to approved specifications, thus not breaching the warranty.

Reasoning: Gibson, under its warranty, did not guarantee the design or specifications of the building wall system; it only warranted new materials from STO that were installed correctly.

Defenses Related to Payment Terms in Construction Contracts

Application: The court addressed whether payment to Gibson was contingent upon approval from the architect and the owner, finding that such conditions are often deemed ambiguous and typically do not impose a condition precedent.

Reasoning: Article 7 of the subcontract states final payment is due upon completion of work to the satisfaction of the owner and architect, and upon payment from the owner to the contractor.

Interpretation of Ambiguous Contractual Conditions

Application: The trial court interpreted ambiguous payment terms in favor of Gibson, aligning with precedent that views such conditions as not imposing a condition precedent on subcontractors.

Reasoning: The court referenced precedent indicating that such conditions are often considered ambiguous, typically not imposing a condition precedent on subcontractors regarding the owner’s payment to the general contractor.